Essar Power commissions Hazira unit, completes 270mw project – Feedback

Essar Power today said its subsidiary at Hazira in Gujarat has commissioned the second and last unit of 135 mw, making the 270-mw project fully operational now.

The company said commissioning was done in a record 53 days – from IBR hydrotest to final synchronisation – making it among the swiftest in the industry. The first unit was commissioned in July last year. With this, the 270-mw multi-fuel power plant, which is 100 per cent captive to Essar Steel Hazira, is now fully operational. The plant runs on multiple fuels, like coal (both domestic and imported) and corex gas, simultaneously. Essar Power has a target capacity of 6,100 mw, and this commissioning makes 80 per cent, or 4,840 mw, operational now.

http://economictimes.indiatimes.com/industry/energy/power/essar-power-commissions-hazira-unit-completes-270mw-project/articleshow/55710831.cms

About news

We take care of publishing the latest investment news and highlights for Feedback

Leave a Reply

Your email address will not be published. Required fields are marked *